Scheduled Reservoir Release: ENGLEBRIGHT (USACE) California Data Exchange Center
Welcome to CDEC A division of DWR

Scheduled Releases -- ENGLEBRIGHT (USACE) (ENG)

Elevation: 551' · YUBA R basin · Operator: US Army Corps of Engineers

Query executed Friday at 12:44:17   clock

All data back 7days and forward 7days from 03/22/2012 11:57.

The scheduled reservoir release (outflow) reflects releases scheduled by reservoir operators as reported to the Department of Water Resources. Information that appears old or otherwise dated, is the latest reservoir release reported. Unscheduled release changes can occur without notice.

Plot of Reservoir, Scheduled Release

Date   /   Time  REL SCH  
03/20/2012 00:00 4040 cfs
03/21/2012 00:00 4016 cfs
03/22/2012 00:00 3749 cfs
03/22/2012 02:00 3500 cfs
03/22/2012 04:00 3250 cfs
03/22/2012 05:00 3500 cfs
03/22/2012 06:00 3050 cfs
03/22/2012 08:00 2900 cfs
03/22/2012 10:00 2750 cfs
03/23/2012 00:00 2500 cfs
03/24/2012 00:00 2300 cfs
03/25/2012 00:00 2000 cfs
03/26/2012 00:00 1700 cfs
03/27/2012 00:00 1400 cfs
03/28/2012 00:00 1400 cfs

Earlier | Later | Latest

BLB BOC BUC BUL CAS CFW CLK CMN COY DNC ENG FRM GBR GDW HID INC INV ISB KES LEW LGR MCS MIL MRT NAT NHG ORO PIU PNF PRS PVP PYM SCC STP THC TRM UVR WHI WRS

Download Data Now Download Data Now | Show ENG Map | 1 Month ENG Releases | Hourly ENG Data | Daily ENG Data | Monthly ENG Data | ENG Info | New Reservoir Releases | Reservoir Info