Scheduled Reservoir Release: ENGLEBRIGHT (USACE) California Data Exchange Center
Welcome to CDEC A division of DWR

Scheduled Releases -- ENGLEBRIGHT (USACE) (ENG)

Elevation: 551' · YUBA R basin · Operator: US Army Corps of Engineers

Query executed Thursday at 9:11:46   clock

All data back 7days and forward 7days from 06/01/2012 02:14.

The scheduled reservoir release (outflow) reflects releases scheduled by reservoir operators as reported to the Department of Water Resources. Information that appears old or otherwise dated, is the latest reservoir release reported. Unscheduled release changes can occur without notice.

Plot of Reservoir, Scheduled Release

Date   /   Time  REL SCH  
05/26/2012 00:00 2300 cfs
05/27/2012 00:00 2300 cfs
05/30/2012 17:00 2200 cfs
05/30/2012 22:00 2050 cfs
05/31/2012 00:00 2033 cfs
06/01/2012 00:00 1800 cfs
06/02/2012 00:00 1800 cfs
06/05/2012 00:00 1800 cfs
06/06/2012 00:00 1800 cfs
06/07/2012 00:00 1800 cfs
06/08/2012 00:00 1800 cfs

Earlier | Later | Latest

BLB BOC BUC BUL CAS CFW CLK CMN COY DNC ENG FRM GBR GDW HID INC INV ISB KES LEW LGR MCS MIL MRT NAT NHG ORO PIU PNF PRS PVP PYM SCC STP THC TRM UVR WHI WRS

Download Data Now Download Data Now | Show ENG Map | 1 Month ENG Releases | Hourly ENG Data | Daily ENG Data | Monthly ENG Data | ENG Info | New Reservoir Releases | Reservoir Info